01 / 29 / 2020

Once we knew we had secured funding we invested in submitting for our building permit.

And then the coronavirus happened. Thankfully the building department was still open and reviewing documents. The project ended up getting hung up on needing a new soils report (amidst a pandemic) and getting answers regarding questions in the initial review.

Because of the pandemic, all construction was put on hold from April through May anyways, so even if the permit was ready, we couldn't have moved forward. We finally pulled our permit on 06/24/2020, almost five months after submission.